Update on Route 318/219 Reconstruction

Posted on
June 17, 2021
by
Town Hall
Here is an update on the Route 318/219 project east of the Saville Dam.  CONNDOT discovered shallower than expected pavement north of the intersection and that has delayed progress towards completion. The current pavement in place now is just a binder course and they still need to mill from the bridge north of the intersection down to the wing walls as you approach the dam. There will then be a leveling course applied to the pavement north of the intersection and the entire project will get 2 more inches of pavement. They will also get more temporary pavement markings out there soon, since it will be into July or August before the paving is complete

There will be delays when they get back to work on this intersection, but for now, it should be quiet until that happens..